Federal inspectors visited the Broadway facility on March 14, 2025, and found that the nursing home's internal quality committee, the group responsible for spotting dangerous trends before they reach residents, had missed seven distinct areas of concern that inspectors had identified during the same survey. The committee hadn't tracked them, hadn't studied them, and hadn't added them to the facility's improvement plan.
The seven areas were call light delays, smokers, registered dietician recommendations, kitchen hygiene, registered dietician kitchen audits, resident care conferences, and low air loss mattress settings.
Low air loss mattresses are used for residents at risk of pressure injuries. The settings matter. A mattress running at the wrong pressure can accelerate skin breakdown in a bedridden resident faster than staff might notice between checks.
At 1:59 p.m. on the day of the inspection, surveyors sat down with the administrator and the Director of Nursing to review the facility's quality program. The Director of Nursing described what the committee was currently monitoring: falls, urinary tract infections, hospital transfers, residents receiving restorative nursing assistance, infection reports, pest control, and the accuracy of federally required assessments.
It was a reasonable list. It did not include any of the seven problem areas inspectors had flagged.
The administrator told surveyors she had not been aware of the issues identified during the survey. She acknowledged the concerns had not been incorporated into the quality improvement plan. Then she said it was important to add them to promote the highest standard of care for residents.
That statement, offered after inspectors had already documented the gap, is the kind of acknowledgment that appears throughout inspection reports at facilities where the oversight machinery is running but not quite watching the right things. The quality committee met. It had a list. The list just didn't include what was actually going wrong.
Call light delays are among the most consistent predictors of resident harm in nursing home settings. When a resident presses a call light and nobody comes, the consequences range from a resident lying in soiled linens to a resident attempting to get up alone and falling. The facility's quality committee was not tracking this.
Kitchen hygiene failures carry their own risks, particularly for elderly residents whose immune systems offer less protection against foodborne illness. The registered dietician, whose job includes monitoring nutritional care and flagging concerns about food service, had apparently been making recommendations and conducting kitchen audits that the quality committee was not incorporating into its improvement work.
Resident care conferences, the meetings at which care plans are reviewed and updated with input from residents and families, were also on the list of overlooked trends. When those conferences are delayed or incomplete, residents can go weeks or months with care plans that no longer reflect their actual condition.
Inspectors rated the deficiency at the minimal harm level, meaning no resident was documented as having been injured as a direct result of the oversight failure. But the regulatory concern with quality committee failures is precisely that they are upstream problems. By the time a quality committee gap produces documented harm, it has usually been invisible for a long time.
The facility's plan of correction was not included in the inspection materials reviewed. Country Hills Post Acute is located at 1580 Broadway in El Cajon and is certified under provider number 555431.
What the inspection captured, in the administrator's own words, was a facility that learned about seven active problems in its own building from the federal surveyors who walked through the door, not from the committee it had assembled to find them first.
Full Inspection Report
The details above represent a summary of key findings. View the complete inspection report for Country Hills Post Acute from 2025-03-14 including all violations, facility responses, and corrective action plans.
Additional Resources
Data source: This article is based on inspection data downloaded directly from the Centers for Medicare & Medicaid Services (CMS) via Medicare.gov. CMS releases inspection reports in bulk; we publish the findings as documented by state surveyors in the official Form CMS-2567 Statement of Deficiencies.
Plan of correction: The CMS report we receive does not include the facility's plan of correction. Facilities submit plans of correction separately to state survey agencies and those responses may not be reflected in CMS data at the time of publication. The absence of a plan of correction in our data does not mean one was not filed. Readers who want information about corrective steps taken are encouraged to contact the facility directly or their state survey agency.
Corrections may have occurred: Inspection reports reflect conditions observed on the date of the survey. Facilities may have implemented corrections, staffing changes, additional training, or other remediation since the report was issued. We report what CMS provides and encourage readers to seek current information from the facility.
Editorial process: Inspection findings are extracted from CMS source documents and synthesized using AI, reviewed for factual accuracy against the original report by our editorial team.
Corrections: We strive for accuracy in everything we publish. If you believe any fact in this article is incorrect, please contact us with details, and we will review and correct it promptly.
Professional review: All content reviewed by Christopher F. Nesbitt, Sr., NH EMT & BU-trained Paralegal.
Last verified: November 20, 2026 · Our methodology
COUNTRY HILLS POST ACUTE in EL CAJON, CA was cited for violations during a health inspection on March 14, 2025.
The committee hadn't tracked them, hadn't studied them, and hadn't added them to the facility's improvement plan.
Health inspections identify deficiencies that facilities must correct. Violations range from minor documentation issues to serious safety concerns. Review the full report below for specific details and facility response.